Federal court voids DOE order forcing Michigan coal plant to stay online

A federal appeals court has vacated the Energy Department’s emergency order that required the J.H. Campbell coal plant in Michigan to remain operational past its scheduled retirement. The ruling rejects the Trump administration’s attempt to override state reliability planning, though the plant will continue operating temporarily under a separate directive through mid-November.
Key points
- The D.C. Circuit Court of Appeals overturned the federal order that blocked Michigan from retiring the J.H. Campbell Plant in May 2025.
- The court found that the Energy Department overstepped its authority by intervening in state-level reliability planning.
- Keeping the plant open beyond its scheduled retirement has cost approximately $259 million, with losses likely passed to Midwest consumers.
- Consumers Energy, the plant’s operator, stated it is reviewing the ruling but will keep the plant running under a separate DOE directive through mid-November.
- Environmental groups, including the Sierra Club and Environmental Defense Fund, called the ruling a victory against 'unlawful' efforts to keep aging, polluting coal plants online.
Background
This ruling follows a September 2026 decision where the same court rejected an emergency bid by Energy Secretary Chris Wright to keep the Campbell plant online, signaling a broader legal challenge to federal interventions in state energy planning.
How outlets are covering it
AP News and WWMT both confirm the D.C. Circuit’s decision to vacate the order, but AP provides specific financial data ($259 million in losses) and quotes from environmental advocates, while WWMT focuses on the legal outcome and the plant’s location in West Olive, Michigan. Both sources agree that the plant will remain operational temporarily due to a separate DOE directive.
Why it matters
The decision sets a precedent for challenges to federal emergency orders affecting other coal plants, potentially influencing the future of six additional aging facilities across the country and impacting energy costs for Midwest consumers.
What to watch
Consumers Energy will continue operating the plant under the existing DOE directive through mid-November, while environmental groups plan to challenge other similar federal extensions. The Energy Department may appeal the ruling, and the court’s decision could influence future cases involving state reliability planning.
- Federal court rejects Trump order keeping Michigan coal plant open AP News
- Court Strikes Down Trump Order to Keep an Aging Coal-Burning Plant Running The New York Times
- Federal court rejects Trump administration order keeping Michigan coal plant open PBS
- A federal judge just told Trump there's no ‘emergency' to justify keeping a Michigan coal plant open grist.org
- D.C. Circuit Appeals Court overturns order keeping Michigan’s J.H. Campbell Plant open WWMT
Want the full story? Read the original reporting
Read on AP News