Boeing absorbs $280M hit to keep 2028 Air Force One delivery on track

Boeing is spending an additional $280 million to accelerate the production and certification of the next-generation Air Force One, aiming to deliver the first aircraft by 2028. This latest cost overrun pushes the program's total losses for the manufacturer beyond $3.1 billion. The company is expanding its workforce and shifting to a military-led certification process to overcome delays caused by complex engineering challenges, including wiring and structural repairs. Meanwhile, the US continues to use a Qatar-donated 747 as an interim presidential aircraft, which lacks the full security capabilities of the new fleet.
Key points
- Boeing committed an extra $280 million in the second quarter to add resources for building and testing the VC-25B aircraft.
- The total cost overruns for the program have exceeded $3.1 billion, which Boeing is absorbing under a fixed-price contract.
- The company is transitioning from an FAA-led to a military-led certification framework to streamline the approval of specialized systems.
- The first VC-25B is expected to begin flight testing in 2027, with delivery targeted for 2028.
- The new aircraft will feature secure communications and advanced medical facilities but will lack the aerial refueling capability of the current fleet.
Background
The current VC-25A fleet has been in service since the 1990s and was deemed in need of replacement in 2015. In 2018, a fixed-price contract was signed to cap costs at $3.9 billion, though the price has since risen to approximately $4.5 billion. In mid-2026, the US Air Force began using a Qatar-donated 747 as an interim 'Bridge' Air Force One after rapid security upgrades, as the permanent replacement faced significant delays.
How outlets are covering it
CNN emphasizes the financial impact on Boeing, noting a $428 million quarterly loss and highlighting that former CEO Dave Calhoun previously called the fixed-price contract 'risky.' Luxurylaunches focuses on the technical and logistical efforts, such as the shift to military certification and supply chain diversification, to meet the 2028 deadline. Both outlets agree that the Qatar-donated interim aircraft lacks the full defensive and mission capabilities of the permanent fleet, with CNN noting President Trump's decision to return to the older VC-25A for a recent trip due to security concerns.
Why it matters
The Air Force One program is a high-profile defense project that reflects the complexities of modern military aviation procurement. The massive cost overruns and schedule delays highlight the risks of fixed-price contracts for highly specialized aircraft. The transition to a new certification process and the use of an interim foreign-donated aircraft also raise questions about national security and the long-term viability of the presidential fleet.
What to watch
Boeing and the US Air Force are expected to finalize revised contract terms later in 2026. The first VC-25B is scheduled to begin flight testing in 2027, followed by certification and delivery in 2028. In the interim, the US will continue to use the Qatar-donated 747 and the aging VC-25A fleet for presidential travel.
- As if absorbing $3 billion was not enough, Boeing is spending an additional $280 million to ensure that the new Air Force One is not delayed a single bit, adding workers to deliver the advanced presidential fortress in 2028 and finally replace the luxurious 747 Luxurylaunches
- Boeing Spends Big to Meet Deadline for New Air Force One WSJ
- The new Air Force One just got a big update - and price tag CNN
- Boeing’s VC-25B losses deepen as company pushes to meet 2028 deliveries FlightGlobal
- Boeing results dragged down by Air Force One refurbishment costs Financial Times
Want the full story? Read the original reporting
Read on Luxurylaunches