Belgian regional authorities have ordered Google to stop construction on a large data centre in Farciennes after the company continued building despite a revoked planning permit. Inspectors found the 30,000-square-meter structure nearly complete and issued a verbal stop order to 300 workers on November 26. The dispute centres on Google's attempt to merge two smaller air-cooled facilities into one larger water-cooled centre, which was rejected in August due to drought concerns. Google has appealed the decision, with a ruling expected from Belgium's Council of State on January 7.

Key points

  • Walloon inspectors visited the site on November 26 and issued a verbal stop order to approximately 300 workers, confirming it in writing to Google.
  • The construction site, located on a former coalmine near Charleroi, features a 30,000-square-meter building that inspectors described as almost finished.
  • Google's 2025 application to switch from air to water cooling and merge two buildings was approved in April but revoked in August by Minister François Desquesnes over water usage concerns.
  • Greenpeace filed an emergency appeal after satellite images revealed ongoing construction despite the permit revocation, prompting the regulatory intervention.
  • Google has appealed the permit annulment to Belgium's Council of State, with a public hearing scheduled for January 7, 2027.

Background

This incident follows a series of regulatory challenges for Google's European data centre expansion. In October 2026, Finnish authorities halted construction of two AI data centres in northern Finland after the company was accused of illegally clear-cutting approximately 400,000 trees without completing environmental impact assessments. That case led to a criminal investigation and a national debate over the environmental costs of AI infrastructure. The Belgian dispute adds to a pattern of legal and environmental friction surrounding Google's €5 billion investment in Belgian cloud and AI infrastructure over two years.

How outlets are covering it

The Guardian and MLQ.ai emphasize the legal and procedural aspects, noting that the original 2024 permit for three air-cooled buildings remains valid, while the modified 2025 permit was revoked. Data Center Dynamics highlights the environmental conditions attached to the permit, including requirements for carbon-free energy and sustainable cooling. Greenpeace, cited by multiple outlets, frames the continued construction as 'disrespectful to the environment, local residents, and the law,' arguing that energy-intensive data centres cannot be built without public debate. Google, in contrast, maintains it is committed to 'open and collaborative dialogue' and has halted work pending further guidance from authorities.

Why it matters

The halt underscores the growing tension between tech giants' rapid AI infrastructure expansion and local environmental regulations in Europe. As data centres become major water and energy consumers, authorities in Belgium and Finland are increasingly scrutinizing permits and construction practices. The case may set a precedent for how regulatory bodies enforce planning conditions in the face of large-scale corporate investments, potentially influencing future AI data centre projects across the continent.

What to watch

Google is expected to comply with the stop order while awaiting the Council of State ruling on January 7, 2027. If the appeal fails, the company may be required to revert to the original 2024 plan for three smaller air-cooled buildings or face further legal consequences. Regional authorities may also pursue criminal charges for the illegal construction of the 3-hectare building, as indicated by a report to public prosecutors.