Construction bridge in Old Town collapses into river, injuring three

2 min read
Source: Bangor Daily News
Construction bridge in Old Town collapses into river, injuring three
Photo: Bangor Daily News
TL;DR

A replacement bridge under construction in Old Town, Maine, collapsed into the Stillwater River on Thursday afternoon, injuring three workers. The incident occurred during a concrete pour, and while the structure failed, the temporary bridge used for traffic remained intact.

Key points

  • The Llewellyn Estes Bridge, carrying Stillwater Avenue over the Stillwater River, collapsed shortly after 2 p.m. on August 13, 2026.
  • Three individuals sustained non-life-threatening injuries; the injured were transported to the emergency room, though the nature of the injuries remains unclear.
  • The collapse happened while construction crews were pouring concrete for the bridge deck, according to the Maine Department of Transportation (MaineDOT).
  • The bridge was closed to traffic during construction, and motorists were not impacted by the collapse.
  • A temporary bridge at the site remained intact and was reopened to traffic by 2:50 p.m., while crews worked to clear debris from the river.

Background

The Llewellyn Estes Bridge replacement project has been underway for years, with MaineDOT sharing progress updates as recently as June 2026, which noted preparations for concrete pours. The collapse occurred during a critical construction phase, highlighting the risks involved in bridge reconstruction projects.

How outlets are covering it

Outlets reported varying numbers of injuries: Bangor Daily News initially reported one injury, while WABI, WGME, and WMTW reported three non-life-threatening injuries. MaineDOT confirmed the collapse during a concrete pour but did not immediately disclose the cause. The Maine Department of Environmental Protection stated it was not involved in cleanup efforts but would monitor the situation. The contractor, Reed & Reed, Inc., did not comment on the incident.

Why it matters

The collapse underscores the risks associated with bridge construction and the importance of safety protocols during critical phases like concrete pouring. It also highlights the need for robust infrastructure maintenance and the potential impact of construction failures on local traffic and safety.

What to watch

MaineDOT is assessing the situation and will release more information on the cause of the collapse. Cleanup efforts are underway to remove debris from the Stillwater River, and the temporary bridge remains in use for traffic. Further updates are expected as the investigation progresses.