Kotek halts Salem data center land sale, Verrus vows to pursue project

Oregon Governor Tina Kotek ordered the state to cancel a land sale to tech firm Verrus for a proposed $5.1 billion data center near Salem. The move blocks a 32-acre state parcel needed for the 75-acre project, which faced intense public opposition over water and energy use. Verrus expressed disappointment but stated it intends to continue pursuing the development in Salem.
Key points
- Kotek directed the Department of Administrative Services to terminate a contract signed in May 2025 for the sale of 32.23 acres at the Mill Creek Corporate Center.
- The land constitutes half of the 75-acre site Verrus planned for its 'Oakline at Mill Creek' project, valued at $5.1 billion.
- Verrus, a California-based company funded by Google, called the decision unilateral and stated it remains committed to the project.
- Salem City Council is scheduled to meet on August 3 to discuss a potential moratorium on AI data centers.
- Kotek cited concerns regarding infrastructure, natural resources, and community impact as reasons for the withdrawal.
Background
This decision follows a broader state effort to regulate data centers, including the formation of a Statewide Data Center Advisory Committee in January 2026 and recent rate hikes for large energy users under the POWER Act. The Salem project had been under a non-disclosure agreement with the city since March 2025, leading to public outcry when details emerged in July.
How outlets are covering it
KATU and Salem Reporter highlight the intense public backlash, with residents protesting at city council meetings over environmental and infrastructure concerns. Verrus, as reported by Salem Reporter and Statesman Journal, argued the decision was made without proper consultation and that the project would offer community benefits and efficient resource use. Statesman Journal notes that while the state land sale is cancelled, Verrus intends to pursue the project, potentially using adjacent private land. Salem Reporter raises questions about the transparency of the initial non-disclosure agreement and the political motivations behind the governor's move.
Why it matters
The decision sets a precedent for state intervention in large-scale private development projects and highlights the growing tension between economic development and environmental/community concerns regarding AI infrastructure. It may influence future data center proposals across Oregon and other states.
What to watch
Salem City Council will meet on August 3 to vote on a potential moratorium for AI data centers. Verrus plans to continue its pursuit of the project, potentially through alternative land arrangements. The Statewide Data Center Advisory Committee is scheduled to meet on July 31 and August 4 to discuss policy recommendations.
- Gov. Tina Kotek orders Oregon to withdraw land sale for Salem-area data center KATU
- Oregon governor blocks sale of state land for Salem data center OregonLive.com
- Verrus surprised, disappointed by Kotek's move to block sale of 32-acres of land at Mill Creek Corporate Center Salem Reporter
- ‘Signing the city’s death warrant’: Salem residents push back against proposed data center at contentious council meeting KOIN.com
- Gov. Tina Kotek orders state to kill land sale for Salem data center Statesman Journal
Want the full story? Read the original reporting
Read on KATU