Maryland cancels Key Bridge Phase 2 contract, testing Moore's speed claim

1 min read
Source: WBFF
Maryland cancels Key Bridge Phase 2 contract, testing Moore's speed claim
Photo: WBFF
TL;DR Summary

Maryland canceled its Phase 2 contract with Kiewit for the Francis Scott Key Bridge after bids exceeded state estimates, forcing a rebid as costs balloon from about $1.8B to over $5B; Gov. Wes Moore defends a fast, safe rebuild while USDOT emphasizes taxpayer protections and oversight, with MDTA planning an industry forum to select a new contractor and Phase 1 work continuing.

Share this article

Reading Insights

Total Reads

1

Unique Readers

2

Time Saved

6 min

vs 7 min read

Condensed

95%

1,24762 words

Want the full story? Read the original article

Read on WBFF