Thermal Footage Exposes Illegal Gas Generators at New Jersey AI Data Center

3 min read
Source: The Guardian
Thermal Footage Exposes Illegal Gas Generators at New Jersey AI Data Center
Photo: The Guardian
TL;DR

Thermal drone footage reveals that the DataOne facility in Vineland, New Jersey, is operating at least 45 unpermitted gas-powered generators. This violates federal law and has drawn criticism from former EPA officials, who argue the company should cease operations immediately. The site, part of a $17 billion deal with Microsoft and Nebius, faces ongoing legal and regulatory challenges due to noise complaints and lack of proper environmental permits.

Key points

  • Thermal drone footage captured by the non-profit newsroom Floodlight shows at least 45 of the 62 generators at the DataOne facility in Vineland, New Jersey, are operational.
  • The New Jersey Department of Environmental Protection (NJDEP) confirmed that no permits have been issued or are under review for these power generators, despite their operation since late June or October.
  • Former EPA air enforcement chief Bruce Buckheit stated that the unpermitted operation violates federal law and should result in immediate cessation and fines for illegal emissions.
  • The facility is part of a $17 billion deal between Microsoft and Dutch AI infrastructure firm Nebius, intended to provide AI computing power.
  • Local residents have filed a class-action lawsuit over noise pollution, while the city of Vineland issued stop-work orders in September for moving fuel cells without permission.
  • DataOne originally planned to use Bergen gas-burning engines but withdrew the application in May, opting instead for Bloom fuel cells, which still require interim power from the unpermitted generators.

Background

This incident follows a broader trend of 'bring your own power' strategies in AI data centers, where facilities build on-site gas plants to bypass grid constraints. Similar controversies have arisen in Texas and along the Tennessee-Mississippi border. In New Jersey, DataOne is the first to attempt this model, facing significant local opposition and regulatory scrutiny due to environmental and noise impacts.

Why it matters

The case highlights the growing tension between rapid AI infrastructure expansion and environmental regulations. Unpermitted operations raise concerns about public health, air quality, and the enforcement of federal and state laws. It also underscores the potential for regulatory gaps in the booming AI data center sector, where speed to market may be prioritized over compliance.

What to watch

The NJDEP is expected to make a full compliance determination regarding the unpermitted generators. If enforcement action is taken, it could lead to fines and a stop-work order. DataOne must either secure permits or cease operations, while the transition to Bloom fuel cells remains pending. Local residents and regulators will likely continue to monitor the site for further violations.