El Paso County rules Buc-ee’s fits local zoning, ending public debate over I-25 site

El Paso County commissioners voted 4-1 to classify a proposed Buc-ee’s travel center as a 'convenience store' under local zoning rules. This decision clears the final public hurdle, allowing the project to proceed through administrative review without further public hearings.
Key points
- The vote on August 27, 2026, determined that the 74,000-square-foot development at County Line Road and Interstate 25 qualifies for the C-1 commercial district.
- Commissioners Carrie Geitner, Holly Williams, Cory Applegate, and Lauren Nelson approved the appeal; Bill Wysong was the sole dissenter.
- The decision does not approve construction but allows the project to move forward via administrative staff review for traffic, lighting, and parking compliance.
- The hearing lasted over eight hours with more than 160 speakers, the vast majority opposing the project, at Centennial Hall in Colorado Springs.
Background
The dispute began in late 2024 when Buc-ee’s sought annexation into Palmer Lake, which it later withdrew. In June 2026, the county planning department could not administratively determine if the site fit the C-1 zoning code, prompting the appeal. The land has been zoned commercial for nearly 70 years.
How outlets are covering it
The Colorado Springs Gazette and The Denver Post highlighted the commissioners' focus on the literal text of the zoning code, noting that Chair Geitner argued the code does not cap store size. Colorado Public Radio emphasized the opposition's argument that the development is a 'travel plaza' rather than a neighborhood convenience store, citing the 120 gas pumps. KKTV clarified that the vote only classifies the use and does not approve the site development plan, which remains subject to technical staff review. Opponents, including former Mayor John Suthers, argued the project serves interstate travelers rather than local residents, while supporters cited economic benefits and the lack of size restrictions in the code.
Why it matters
The ruling eliminates the final public input stage for the project, shifting the process to technical administrative review. This sets a precedent for how large commercial developments are interpreted under existing zoning codes in El Paso County, potentially affecting future land-use disputes in the Tri-Lakes area.
What to watch
Buc-ee’s must submit a site development plan to county staff. If the plan meets technical requirements for traffic, lighting, and landscaping, it will be approved administratively without further commissioner or public hearings. Opponents have indicated they may pursue other legal or regulatory options, including contacting the Federal Highway Administration.
- El Paso County upholds Buc-ee’s zoning appeal, clearing way for administrative approval Colorado Springs Gazette
- New proposed Buc-ee's location in El Paso County will move forward without public hearings after appeal passes Colorado Public Radio
- El Paso County commissioners find Buc-ee’s allowed in zoning district KKTV
- Buc-ee’s labeled as convenience store in El Paso County FOX21 News Colorado
- El Paso County rules Buc-ee’s as ‘convenience store’ The Denver Post
Want the full story? Read the original reporting
Read on Colorado Springs Gazette