Texas Lifts Data Center Moratorium Ahead of Hinojosa's January Arrival

Outgoing Texas Governor Greg Abbott reversed his September moratorium on data center approvals, allowing the state to resume permitting new projects. This move creates a two-month window for developers to secure permits before incoming Governor Gina Hinojosa takes office in January, a period during which she has pledged to reinstate strict restrictions on data center construction.
Key points
- Abbott's office directed the Texas Commission on Environmental Quality to resume issuing permits after pausing them in September to protect public safety and quality of life.
- The moratorium had suspended 474 gigawatts of grid-connected power requests and 17 specific construction permits pending an investigation by the Electric Reliability Council of Texas (ERCOT).
- Incoming Governor Gina Hinojosa, who defeated Abbott in the November 3 election, is scheduled to take office in January, creating a gap where new permits can be issued before her promised moratorium takes effect.
- SpaceX is among the first to benefit, with its $24 billion data center project in the Rio Grande Valley receiving approval; the project includes a dedicated gas-fired power plant with 35 turbines producing 750 MW.
- State Representative-elect Cecilia Castellano filed House Bill 1273, which would require large data centers to pay residents annually and give local voters a direct vote on project approvals.
Background
Abbolt initially imposed the moratorium in September 2026, citing concerns over the strain data centers place on local infrastructure and the environment. This decision preceded the November 3 midterm elections, where Hinojosa campaigned on a platform that included ending data center 'madness' through an immediate moratorium. Hinojosa's victory triggered a sell-off in AI-linked stocks due to fears of stricter state-level regulations. Prior to the recent lifting of the moratorium, SpaceX had announced a $74 billion investment in Texas and Arizona, including a $24 billion project in Starbase that bypassed local restrictions by using land de-annexed from Brownsville.
How outlets are covering it
Gizmodo characterizes the lifting of the moratorium as 'unabashed corporate-sponsored cynicism,' arguing that Abbott's initial pause was a political maneuver to sway voters who were opposed to data centers, only to be reversed immediately after the election. Tom's Hardware frames the move as a strategic pivot by Abbott's office to allow developers to secure permits before Hinojosa takes office, noting that some companies are building their own power sources to bypass grid constraints. Click2Houston highlights a legislative response, detailing House Bill 1273, which aims to impose financial penalties and voter approval requirements on large data centers, reflecting a growing political push to regulate the industry's impact on local communities.
Why it matters
The lifting of the moratorium accelerates the construction of large-scale data centers in Texas, which are significant consumers of energy and water. This move intensifies the debate over the environmental and social costs of AI infrastructure, as well as the political power of tech companies to influence state policy. The impending arrival of Governor Hinojosa, who has pledged to reinstate restrictions, creates a critical window for developers to secure approvals, potentially locking in projects that would otherwise be blocked.
What to watch
Hinojosa is scheduled to take office on January 19, 2027, at which point she is expected to implement her campaign promise of a moratorium on data center construction. Developers are expected to continue rushing to secure permits in the two-month window before her arrival. The Texas legislature may consider House Bill 1273, which would require large data centers to pay residents and undergo local voter approval, potentially altering the regulatory landscape for future projects.
- Texas Governor Ends Moratorium On Data Centers Gizmodo
- With Abbott out, what does the future look like for data centers in Texas? NPR
- Texas resumes data centre permitting before Democrats take over Financial Times
- Could a data center in your county pay you every year? This Texas bill would make it possible Click2Houston
- Texas lifts freeze on 1,800+ data center projects in Greg Abbott U-turn — companies rush for permits before Gina Hinojosa's January arrival Tom's Hardware
Want the full story? Read the original reporting
Read on Gizmodo