NIST Finds Early Garage-Column Failures Triggered Champlain Towers South Collapse

TL;DR
NIST's NCST technical findings attribute the Champlain Towers South collapse to punching shear failures at two garage column connections in early June 2021, which caused cracks, load redistribution, and eventual collapse; margins against failure were too narrow due to design and construction deviations from codes, ongoing loads, and corrosion, with other potential factors ruled out; a final report with recommendations will follow.
Topics:nationscience#building-safety#champlain-towers-south#nist-ncst#punching-shear#science#structural-engineering
- NIST Releases Technical Findings on What Caused the 2021 Partial Collapse of Champlain Towers South National Institute of Standards and Technology (.gov)
- Federal investigators say deadly Surfside building collapse began 3 weeks prior ABC News - Breaking News, Latest News and Videos
- Collapsed Surfside Condo Had Been Failing for Weeks, Investigators Find The New York Times
- New report says Surfside collapse was set in motion weeks earlier. What we know now Miami Herald
- Federal investigators release cause of Surfside condo collapse WPLG Local 10
Want the full story? Read the original reporting
Read on National Institute of Standards and Technology (.gov)