Palisades Reactor Begins Fuel Loading, Enters Refueling Mode After Four-Year Hiatus

Holtec International began loading fuel into the Palisades Nuclear Power Plant on August 30, 2026, marking the first time fuel has entered the reactor since its 2022 shutdown. The plant is now in 'Mode 6' (refueling), with eight of 204 fuel assemblies installed. While no restart date is set, the move signals a major step toward returning the 805-megawatt facility to the grid by March 2027.
Key points
- Fuel loading began on August 30, 2026, with eight of 204 assemblies installed by August 31.
- The plant is now in 'Mode 6' (refueling), the first step in a defined progression toward restart.
- Some fuel assemblies are the same ones removed in 2022; 68 new assemblies were added in October 2025.
- No specific restart date has been announced, but a contractual deadline for power delivery is March 2027.
- The restart follows a two-year refurbishment process, including repairs to 1,163 cracked steam generator tubes.
Background
Palisades, an 805-megawatt plant in Covert Township, Michigan, ceased operations in May 2022 and was emptied for decommissioning by June 2022. Holtec International acquired the plant and began a multi-year refurbishment process, including repairs to steam generators and installation of new fuel handling equipment. The plant is the first in U.S. history to attempt a restart after full defueling for decommissioning.
How outlets are covering it
Holtec International, via spokesperson Nick Culp, emphasized that fuel loading is a major milestone and the first step in a defined progression toward restart, but declined to provide a specific timeline. The Holland Sentinel and WSBT reported on the fuel loading as a significant step toward restart, noting the plant's 805-megawatt output and the two-year refurbishment process. WSJM highlighted the plant's entry into 'Mode 6' (refueling) and the need for further testing and inspections before restart. All sources agree on the significance of the fuel loading but differ in emphasis: Holtec focuses on the technical progression, while local outlets focus on the milestone and timeline uncertainty.
Why it matters
The restart of Palisades is significant for Michigan's energy grid, as it will provide carbon-free baseload power to two rural electric cooperatives, Wolverine Power Cooperative and Hoosier Energy, which have contracted for 100% of the plant's output. The plant's restart also sets a precedent for other decommissioned reactors, such as Three Mile Island and Duane Arnold, which are also pursuing restarts. The success of Palisades could impact the future of nuclear energy in the U.S. and the grid's ability to meet demand for carbon-free power.
What to watch
Holtec will continue loading the remaining 196 fuel assemblies and proceed through Modes 5 through 1, which involve testing, inspections, and operational readiness activities. The plant will not be online until all technical specifications and federal requirements are met. A specific restart date has not been announced, but a contractual deadline for power delivery is March 2027.
- A crane lowered eight 12-foot fuel bundles into a reactor on the Lake Michigan shore on Sunday, 196 short of a full core, four years after the vessel was emptied for scrapping, and some of the bundles going back in are the ones that were in it when it shut down Autonocion.com
- Holtec begins loading fuel into reactor vessel at Palisades The Holland Sentinel
- Palisades Nuclear Plant one step closer to restart as fuel loading begins WSBT
- With reactor fueling underway, Palisades enters new phase of restart effort News/Talk/Sports 94.9 WSJM
- Palisades power plant starts loading nuclear fuel WOODTV.com
Want the full story? Read the original reporting
Read on Autonocion.com